Saturday, April 23, 2011

Touhoku area need electric power2

23 April by Tohoku electric co
The number of units currently blackout
Iwate pref 27412
Miyagi pref 79671
Fukushima pref 34567
Total 141650

Thermal power plants
hachinohe Thermal Power Plant Unit 3 - driving
Noshiro Thermal Power Station Unit 1,2-driving
Akita Thermal Power Plant Unit 4 - driving
Sendai Thermal Power Station Unit 4: Down
New Sendai Thermal Power Station Unit 1 ,2- Down
Inside Sendai thermal power station

Haramachi Thermal Power Station Unit 1,2 - Down
Haramachi thermal power plant by hokkaido np
Hydro facilities
Tagashiro hydro facility by denki shinbun


Equipment damage 11
Building falling rock,sediment influx 2
Electric substation equipment
Equipment damage 22
Transformer damage 84, Breaker damage  198, Disconnector injury 195
Transmission plant
Equipment damage 28, Inclined pylon fracture damage 42,
Broken insulator wire breakage 32,Underground cables damaged 15,Landslide 20
Distribution plant
17 April Iwanuma city
 A Tohoku electric power worker replace cable.


Breakage or tilt support 25409
Broken or shot circuit wire 31708
Damage to transformers and switchgear 8847

Electric power car runs 24 hours in Ojika Ishinomaki city by here

24 April

The number of units currently blackout
Iwate pref 27163
Miyagi pref 78593
Fukushima pref 34567
Total 140323

Thermal power plants
hachinohe Thermal Power Plant Unit 3 - driving
Noshiro Thermal Power Station Unit 1,2-driving
Akita Thermal Power Plant Unit 2-4 - driving
Sendai Thermal Power Station Unit 4: Down
New Sendai Thermal Power Station Unit 1 ,2- Down
Haramachi Thermal power plant unit 1,2-down

Hydro facilities

Equipment damage 11
Building falling rock,sediment influx 2
Electric substation equipment
Equipment damage 22
Transformer damage 84, Breaker damage  198, Disconnector injury 195
Transmission plant
17 march oozuchi town by here

Equipment damage 28, Inclined pylon fracture damage 42,
Broken insulator wire breakage 32,Underground cables damaged 15,Landslide 20
5 April Kamaishi city Iwate pref by mainichi news paper
Distribution plant
Breakage or tilt support 25409
Broken or shot circuit wire 31708
Damage to transformers and switchgear 8847
Touhoku electric co,developed their original Aerial work platforms truck 
with seismic equipment in 2010.

Situation and future prospects of recovery from power failure earthquake and Tsunami
  1. Our facilities and the impact of TSUNAMI, public infrastructure, regional customers house was destroyed, etc.
  2. Released due to restricted access and debris removal in the future, the region's recovery efforts can be initiated.
  3. Our facilities recovered but customer can not hold the power house wiring checked for safety due to the evacuation,etc
By Touhoku electric co.ltd, count is unit(house).


28 April 

Thermal power plants
Sendai Thermal Power Station Unit 4: Down
New Sendai Thermal Power Station Unit 1 ,2- Down
Haramachi Thermal Power Station Unit 1,2 - Down
Hydro facilities

Equipment damage 11
Building falling rock,sediment influx 2
Electric substation equipment
Equipment damage 19
Transformer damage 86, Breaker damage  198, Disconnector injury 195
Transmission plant


Equipment damage 28, Inclined pylon fracture damage 42,
Broken insulator wire breakage 32,Underground cables damaged 14,Landslide 20

Distribution plant
Breakage or tilt support 26570
Broken or shot circuit wire 33121
Damage to transformers and switchgear 9010



If you wanted passed information please visit this page